Week 2
September 2008
Filling 1    Filling 2 

Filling 3    Filling 4 
Excavators bring soil into the creek crossing to provide a temporary work area. 
The work area will be used by a drill rig that will install the bridge supports.

Filled 
The temporary work area is complete. 

 

Survey 

Surveyors mark the exact locations of the bridge supports in preparation of drilling.

 


  

Drill Rig

  The drill rig arrives at the site.


  

Drill Crew    Drill Crew 2

  The drilling crew prepares the equipment. 

Twelve vertical holes will be drilled to support the bridge over Carpinteria Creek.

 


 Drill Bit

The huge drill bits that will be used to carve through the rocky native soils of this region. 


 

Archive:
Week 1      Week 2      Weeks 3&4     Weeks 5&6     Weeks 7-9     Weeks 10-12 

 

Bliss Project Home

 

 

 


Home  Carp Creek  The Coalition

Projects  Documents  Links 

 ©Carpinteria Creek Watershed Coalition

Last updated Sept 15, 2008

 

Email

©Carpinteria Creek Watershed Coalition