Bliss Project Home
Project Summary

Click images for full-size photos tracking the progress of this restoration project.

Archive:
Week 1      Week 2      Weeks 3&4     Weeks 5&6     Weeks 7-9     Weeks 10-12 

Week 1
September 2008

Pre-Construction 
Before construction, the Arizona crossing poses a major barrier to fish migration. 
This photo is from the wet season; Carpinteria Creek dries out at this location in summer.

 
TreeGrub 
A few trees and shrubs were removed from the creek banks to allow access. 
Disturbed soils will be restored with native plants at the end of the construction process. 
 

Breaking 2     Breaking 3

    

Breaking 4     Breaking 5

 An excavator with a "breaker" attachment begins to crack and remove the old concrete slab.

Several layers of concrete were discovered under the top slab.

 


 Hauling 1     Hauling2

  Concrete and rebar remnants are excavated out of the channel

and hauled away for recycling.

 


 filling     filling 2

  Rock residue is used to fill the eroded gap downstream of the old slab.


regrading

The creek channel is re-graded to provide a consistent slope. 


 

Archive:
Week 1      Week 2      Weeks 3&4     Weeks 5&6     Weeks 7-9     Weeks 10-12 

 

Bliss Project Home

 

 


Home  Carp Creek  The Coalition

Projects  Documents  Links 

 ©Carpinteria Creek Watershed Coalition

Last updated Sept 8, 2008

 

 

Email

©Carpinteria Creek Watershed Coalition