Bliss Project Home
Project Summary
Click images for full-size photos tracking the progress of this restoration project.
Archive:
Week 1 Week 2 Weeks 3&4 Weeks 5&6 Weeks 7-9 Weeks 10-12
Weeks 7-9
October 2008
The wood frame is stripped from the first bridge abutmet and soil is backfilled to
prepare the road base.
Wood and metal framing continues at the second bridge abutment.
Restoration of the creek channel begins. First, the channel is graded to a stable slope.
|