Weeks 5 & 6
October 2008
The final bridge supports are drilled and poured with concrete and the rebar cages are installed.
The drilling operation de-mobilizes and removes water tanks and equipment from the site.
Wood and metal framing begins at the second bridge abutment.
Framing for the bridge abutments continues. The wood elements creates a mold for the concrete.
|