Bliss Project
Project Summary
Click images for full-size photos tracking the progress of this restoration project.
Archive:
Week 1 Week 2 Weeks 3&4 Weeks 5&6 Weeks7-9
Weeks 10-12
November 2008
The pre-fabricated bridge is delivered in two sections by semi trucks.
The first bridge section is hoisted into the air with a crane, and carried over the bridge abutments.
Crews guide the end of the bridge into the concrete abutments and fasten the
end pieces of the guard rails.
The process is repeated with the second bridge section.
|